Sutton Takes First Step Toward Replacing Damaged Pudding Hill Road Bridge
SUTTON — Cracks in the concrete walls of the Pudding Hill Road bridge continue to worsen, and Sutton officials have taken a first step toward replacing it. The Select Board agreed Oct. 29 to contact an engineer about a project expected to cost more than $2 million, a sum the small town cannot afford alone. The town’s road foreman, Shane Heath, raised the issue at the board’s Oct. 29 meeting. He said state Agency of Transportation project manager Logan Perron had recommended two engineering firms for the bridge, which officials referred to as Bridge No. 4. The bridge is among the most expensive remaining problems from a July 10, 2025, storm that caused more than $3 million in damage in Sutton. The town has received no Federal Emergency Management Agency reimbursement after President Donald Trump denied Vermont’s request for a disaster declaration.